Permits and inspections: a realistic timeline

What actually happens between signing a contract and framing inspection, and where the weeks really go.

Framed addition interior with open stud walls, wiring, and plumbing before insulation

Design and engineering come first

Before anything is submitted, you need drawings that a plan reviewer can read and, for structural work, an engineer's stamp. This stage is driven by decisions — yours. Projects rarely wait on the jurisdiction here; they wait on selections and sign-off.

Plan review is not a fixed number

Review times vary by jurisdiction, season, and how complete the submittal is. A clean, complete package gets through faster than a thin one, and a correction request restarts part of the clock. We build a realistic window into the schedule rather than promising a date the county has not agreed to.

Inspections punctuate the build

Typical sequence on a permitted addition: footing, foundation, underfloor, framing, rough mechanical, rough electrical, rough plumbing, insulation, drywall nail, then final. Work stops at each hold point until the inspector signs off, so scheduling them tightly is a real part of keeping a job on time.

Who chases it matters

On our projects one person owns permits and inspections end to end — submitting, answering corrections, and booking inspectors. You should never be the one calling the county to find out where your project stands.